Late in 2005 construction began on a major addition to our church complex.
This series of photos taken during construction show what the site looked like
during the various stages of cosntruction (including re-doing the parking lots).
2005 - We Began to Build
February: We completed the first project, adding an elevator in the narthex.
April: Submitted the building permit application to New Castle County.
A "before" photo of the area where the new building will be built.
July: Signed the construction contract and began clearing the surface on the site.
October: Started excavation to allow pouring the foundation.
The excavated soil was trucked to the back of the upper parking lot and used
to build "Mt. McFall", which was later used as fill around the foundation.
Another view showing the base plates used to secure the main support columns.
Giant steps are footers for the eastern wall.
New light fixtures brighten the path from the main lot to the church