June 2 and 4: Completing and Covering the Shell with a Roof and Walls


All of the roof insulation and sheeting has been installed,
as well as some horizontal brackets for attaching siding panels.


This view from the intersection shows the size of the new facility
compared to the current church facilities.


June 12: Interior Work Begins


The office building disappeared from view (from the cemetery wall near the church entry).


The workers began installing heating /AC ducts and drain pipes.


The siding next to the office building has no windows or other decoration.


The siding on the street side was nearly complete, and soon the smaller roofs
would be covered. Note: The upper right windows are not fully cut out here.


June 22: Parking? A Pause during Summer


For several months we lost the use of the ground floor parking lot.


Here are the storm drain manifolds soon to be buried there.
Mt. McFall returned to its former size, joined by Mt. Brandt (the one in front)
With less space for cars in the upper lot many more parked in the cemetery lot.


Both large and small windows were put in with a special bucket lift.


Sealing and roofing reqiured large work crews.


The air handling pipes were hung from the rafters.